1. Certification letter

Abatement certification · draft

To: Area Director, OSHA Wilkes Barre Area Office
Address: as printed on your citation

MAINSTREET MANUFACTURING COMPANY LLC
143 MAHANOY AVENUE, TAMAQUA, PA 18252

The hazards referenced in Inspection Number 1892248 for the violations identified below were corrected as follows:

  1. Citation 1, Item 1 was corrected on date to be entered by: method to be entered Awaiting your confirmation · not certified
  2. Citation 1, Item 2 was corrected on date to be entered by: method to be entered Awaiting your confirmation · not certified
  3. Citation 1, Item 3 was corrected on date to be entered by: method to be entered Awaiting your confirmation · not certified
  4. Citation 1, Item 4 was corrected on date to be entered by: method to be entered Awaiting your confirmation · not certified

I attest that the information contained in this document is accurate and that the affected employees and their representatives have been informed of the abatement.

Signature
Typed or printed name
Title
Date

Signed by the employer or an authorized representative. CiteClock never signs or certifies for you.

2. Item-by-item closeout

Citation 1 · Item 1 · 29 CFR 1910.95(b)(1) · Serious

Noise exposure controls · Plain-English summary, not legal advice

When employees are exposed to sound above the permissible levels in Table G-16 (for example, 90 dBA for 8 hours a day or 115 dBA for a quarter hour or less), the employer must use feasible administrative or engineering controls. If those controls do not bring sound levels within the table, personal protective equipment must be provided and used to bring them within it.

Official text

Dec 4, 2026 per the public record · Verification required, no certification date estimated. Informal settlement on October 19, 2026, per the public record. A settlement or a petition to modify the abatement date can change the date and what has to be certified (29 CFR 1903.19(b)(2)(i)), so check the date against that document. The abatement date in the public record is December 4, 2026.

Public record: No abatement completion recorded in the public data.

Not yet confirmed by the employer. Nothing is certified for this item.

Evidence on file: 0 files

Possible supporting evidence

  • Noise monitoring results
  • Page of your hearing conservation program
  • Audiometric testing schedule (no individual results)
  • Training roster

Serious item: attach documents if your citation says they are required (1903.19(d)).

Suggestions only, not a statement of what OSHA requires or will accept.

Citation 1 · Item 2 · 29 CFR 1910.95(d)(1) · Serious

Serious item under 29 CFR 1910.95(d)(1)

Verification required. No abatement date in the public record. Use the date on your citation.

Public record: Recorded in the public data as corrected during the inspection.

Not yet confirmed by the employer. Nothing is certified for this item.

The public record shows this item as corrected during the inspection. If your citation notes that, no certification is needed for it (29 CFR 1903.19(c)(2)).

Evidence on file: 0 files

Possible supporting evidence

  • Noise monitoring results
  • Page of your hearing conservation program
  • Audiometric testing schedule (no individual results)
  • Training roster

Serious item: attach documents if your citation says they are required (1903.19(d)).

Suggestions only, not a statement of what OSHA requires or will accept.

Citation 1 · Item 3 · 29 CFR 1910.95(g)(1) · Serious

Serious item under 29 CFR 1910.95(g)(1)

Nov 12, 2026 per the public record · Verification required, no certification date estimated. Informal settlement on October 19, 2026, per the public record. A settlement or a petition to modify the abatement date can change the date and what has to be certified (29 CFR 1903.19(b)(2)(i)), so check the date against that document. The abatement date in the public record is November 12, 2026.

Public record: No abatement completion recorded in the public data.

Not yet confirmed by the employer. Nothing is certified for this item.

Evidence on file: 0 files

Possible supporting evidence

  • Noise monitoring results
  • Page of your hearing conservation program
  • Audiometric testing schedule (no individual results)
  • Training roster

Serious item: attach documents if your citation says they are required (1903.19(d)).

Suggestions only, not a statement of what OSHA requires or will accept.

Citation 1 · Item 4 · 29 CFR 1910.95(k)(1) · Serious

Serious item under 29 CFR 1910.95(k)(1)

Nov 12, 2026 per the public record · Verification required, no certification date estimated. Informal settlement on October 19, 2026, per the public record. A settlement or a petition to modify the abatement date can change the date and what has to be certified (29 CFR 1903.19(b)(2)(i)), so check the date against that document. The abatement date in the public record is November 12, 2026.

Public record: No abatement completion recorded in the public data.

Not yet confirmed by the employer. Nothing is certified for this item.

Evidence on file: 0 files

Possible supporting evidence

  • Noise monitoring results
  • Page of your hearing conservation program
  • Audiometric testing schedule (no individual results)
  • Training roster

Serious item: attach documents if your citation says they are required (1903.19(d)).

Suggestions only, not a statement of what OSHA requires or will accept.

3. Employee posting

Employee posting

Notice to employees: abatement certification

Prepared with CiteClock from the employer's certification. This is not an official OSHA-issued form.

MAINSTREET MANUFACTURING COMPANY LLC will certify to the Occupational Safety and Health Administration that the conditions cited in inspection 1892248 and listed below have been corrected. A copy of the certification is available from the employer on request.

Each item below is listed on the final notice once you confirm it.

  • Citation 1, Item 1 (29 CFR 1910.95(b)(1))
  • Citation 1, Item 2 (29 CFR 1910.95(d)(1))
  • Citation 1, Item 3 (29 CFR 1910.95(g)(1))
  • Citation 1, Item 4 (29 CFR 1910.95(k)(1))

Post this notice near the place where each violation occurred, or where affected employees will readily see it, at the same time as or before the certification is sent to OSHA, for 3 working days (29 CFR 1903.19(g)).

Posted on
Removed on
Posted by

4. Where to send it

Where to send this

OSHA Wilkes Barre Area Office

Identified from the office code in the public record (0317700). Send it to the address printed on your citation. OSHA office directory

Keep a copy of everything you send and the date you sent it.

Still needed from you

  • Your confirmation that all 4 items have been corrected, with the date and how
  • A check of your citation for the item the public record shows as corrected during the inspection. If the citation notes it, mark it: no certification is needed for that item (29 CFR 1903.19(c)(2))
  • Verification of 3 abatement dates against your citation, settlement or final order: the public record does not settle them (see each item)
  • The name and title of the person signing
  • Signature of the employer or an authorized representative
  • Abatement dates are shown per the public record. If a settlement, petition or informal agreement changed your dates or items, use those.
  • Certification is generally due within 10 calendar days after each abatement date (29 CFR 1903.19(c)).
  • No certification date is estimated for an item the public record shows as contested, settled or otherwise changed, or for a record not confirmed as Federal OSHA. Those items say "Verification required": check them against your citation, settlement agreement or final order.
  • No certification is required for an item your citation notes as corrected during the inspection (29 CFR 1903.19(c)(2)). The public data may say so too, but your citation is what counts.
  • Only certify items that are actually corrected. Knowingly false statements in documents required by the OSH Act are a federal offense (29 U.S.C. 666(g)).
  • The evidence ideas are suggestions, not a statement of what OSHA requires or will accept for a particular item.
  • 29 CFR 1903.19 on eCFR · Independent software. Not affiliated with OSHA. Not legal advice.