OSHA counts the contest period from the day your company received the Citation and Notification of Penalty, not the day it was issued. Enter that date to see the estimated timeline: contest, informal conference, certification, posting and, if your citation requires them, plans and progress reports.

Your citation response timeline

Enter the date the citation arrived. Nothing is counted until you do, and nothing you enter leaves this page.

The date it arrived (for example, the certified-mail delivery date).
Abatement date (per item) → certification due

Each cited item has its own abatement date on the citation. Certification is generally due 10 calendar days after it (29 CFR 1903.19(c)(1)).

Enter a date

Estimates only, from the dates you enter. CiteClock does not verify your dates. Weekends and observed federal holidays are excluded from working days; special closures or case-specific orders can change the timing. If a settlement or approved petition changed your dates, use those. Confirm with the issuing OSHA area office or a qualified professional. Not legal advice.

Then: your abatement packet

CiteClock drafts the certification letter, a page per cited item and the employee posting from the public record. OSHA publishes records a few weeks after a citation is issued; if yours is not there yet, upload your copy of the citation instead.

See the 18-page sample packet

The rules behind each date

Contest deadline
For a notice of contest, OSHA counts 15 working days from the day your company received the Citation and Notification of Penalty, not the day it was issued. The day of receipt is not counted; the last day is. (29 CFR 1903.22(c))
Informal conference request
You can ask the Area Director for an informal conference, before the 15-working-day contest period ends. A conference, or a request for one, does not extend the contest period. (29 CFR 1903.20)
Abatement certification
Within 10 calendar days after each abatement date, certify to OSHA that each cited violation has been abated. If a settlement or an approved petition changed your dates, those dates are the ones that count. (29 CFR 1903.19(c)(1))
Employee posting
Post a copy of each document you send OSHA, or a summary of it, near the place where the violation occurred, at the same time as, or before, you send it. Leave it up, unaltered and uncovered, for three working days after you send it. (29 CFR 1903.19(g))
Abatement plan (only if your citation requires an abatement plan)
When the time allowed for abatement is more than 90 calendar days, OSHA may require an abatement plan. It is due within 25 calendar days from the final order date. (29 CFR 1903.19(e))
Progress reports (only if your citation requires progress reports)
The citation says which items need progress reports and when the first is due: no sooner than 30 calendar days after the abatement plan. (29 CFR 1903.19(f))

For the full certification rule, see OSHA abatement certification, in plain English.